Renovation and Addition to Church of the Apostles

See below the weekly reports from Hood construction on their progress.
Pictures included!

Saturday
Nov192011

Progress as of 18 November, 2011

Overall Assessment

As almost everyone knows, we passed all inspections and are busy cleaning and asssisting the church in preparing for their first service this Sunday. All subcontractors and their employees that worked on the project are welcome at the service this Sunday at 10a.

 

Work Performed this Week

  • Passed the elevator and final building inspections.
  • Completed brick tile on the interior steps. 
  • Completed the pew installation.
  • Installed kitchen appliances.
  • Demobilized from the jobsite.
  • Prepared punch list.
  • Continueing to touch up paint.
  • Continuing to clean through tomorrow.

 

Work Plan for Week of November 21st

Work on punch list.

Front entrance.

Narthex stairs. Basement common area is complete.Parish hall.The church is building the communion rail.

Thursday
Nov172011

Progress as of 11 November, 2011

We passed the final fire inspection, so the church is free to move furniture into areas that are clean...

Click to read more ...

Monday
Nov072011

Progress as of 04 November, 2011

The phone lines and water meter are installed and the elevator inspection is scheduled...

Click to read more ...

Monday
Oct242011

Progress as of 21 October, 2011

Continued interior painting...

Click to read more ...

Tuesday
Oct182011

Progress as of 14 October, 2011

Flooring continued this week and will be complete in three weeks...

Click to read more ...