Progress as of 18 November, 2011
Overall Assessment
As almost everyone knows, we passed all inspections and are busy cleaning and asssisting the church in preparing for their first service this Sunday. All subcontractors and their employees that worked on the project are welcome at the service this Sunday at 10a.
Work Performed this Week
- Passed the elevator and final building inspections.
- Completed brick tile on the interior steps.
- Completed the pew installation.
- Installed kitchen appliances.
- Demobilized from the jobsite.
- Prepared punch list.
- Continueing to touch up paint.
- Continuing to clean through tomorrow.
Work Plan for Week of November 21st
Work on punch list.
Front entrance.
Narthex stairs.
Basement common area is complete.
Parish hall.
The church is building the communion rail.